---The Disuse and Reconstruction Project 
                        of Changzhao Hydropower Station in Xinchang City, Zhejiang 
                        Province, which was designed by HRC, began power generation 
                        on April 30th, 2011.
                         With an installed capacity of 6000kW 
                        (3กม2000kW) originally, Changzhao Hydropower Station was 
                        disused in Oct. 2010 and then began to be reconstructed 
                        because the service period of its equipment had expired, 
                        which could pose serious safety risks. After reconstruction, 
                        the installed capacity is increased to 6750kW with HLA643-LJ-100 
                        Francis turbine and SF-J2250-12/2150 generator. The governor 
                        and excitation devices are micro-computer based; the inlet 
                        valve adopts self-supporting hydraulic loaded butterfly 
                        valve; the secondary electric equipment adopts computerized 
                        monitoring and controlling system. Currently, it has achieved 
                        the mode of "no one on duty, few people on guard". 
                        (2011-05-03) 
                      